British oil giant BP and its contractors failed to learn from earlier errors and showed an " insufficient consideration of risk" in the massive oil well blowout in the Gulf of Mexico, a group of U.S. scientists have concluded.

In a report released late Tuesday night, a panel of experts convened by the U.S. National Academy of Engineering said that " numerous technical and operational breakdowns" in the Deepwater Horizon oil rig explosion "suggest the lack of a suitable approach for managing the inherent risks, uncertainties, and dangers associated with deepwater drilling operations and a failure to learn from previous 'near misses.'"

"The events also suggest insufficient checks and balances for critical decisions impacting the schedule for 'abandoning' the exploratory well -- or sealing it in transition to production -- and for considering well safety," according to the report, which was commissioned by U.S. Secretary of the Interior Ken Salazar.

"Important decisions made to proceed toward well abandonment despite several indications of potential hazard suggest an insufficient consideration of risks," said Donald Winter, professor of engineering practice at the University of Michigan, and chair of the study committee.

"It's also important to note that these flawed decisions were not identified or corrected by BP and its service contractors, or by the oversight process employed by the U.S. Minerals Management Service and other regulatory agencies," he said.

The report cited numerous decisions that apparently contributed to the accident, beginning with continuing abandonment operations at the Macondo site despite several tests that indicated that the cement put in place after the installation of a long-string production casing was not an effective barrier to prevent gases from entering the well.

"The decision to accept the test results as satisfactory without review by adequately trained shore-based engineering or management personnel suggests a lack of discipline and clearly defined responsibilities," it said.

In addition, several clear failures in monitoring of the well appear to have contributed to its blowout, making ignition "most likely," the report said, adding that the failure of the blowout preventer and several questionable decisions made about the cement process are also factors in the blowout.

A final report is due in the summer of 2011.

Print E-mail Bookmark and Share

Go to Forum >>0 Comments

No comments.

Add your comments...

  • User Name Required
  • Your Comment
  • Racist, abusive and off-topic comments may be removed by the moderator.
Send your storiesGet more from China.org.cnMobileRSSNewsletter
主站蜘蛛池模板: 渝北区| 英德市| 靖远县| 黑山县| 泾源县| 新乡县| 开鲁县| 柳州市| 阳高县| 尉氏县| 青龙| 新民市| 防城港市| 上虞市| 虞城县| 营山县| 图片| 乡城县| 靖远县| 綦江县| 雷山县| 英德市| 阳高县| 镇原县| 邵武市| 康平县| 牟定县| 法库县| 天等县| 金华市| 桃江县| 漠河县| 龙门县| 永和县| 全南县| 临邑县| 正阳县| 哈尔滨市| 敦化市| 会昌县| 清流县|